Checked against the Marketing Discipline Guidelines 2024 (Ver. 1, effective 24.10.2024) on 24 November 2026. Published by MDG Services on 24 November 2026.
What the report records
The checks below are general practice, not MDG rules, except where a clause is cited.
| Part of the Annexure 6 report | What to check before you sign | Clause |
|---|---|---|
| Visit and equipment: purpose of visit, unit name, model, serial number, product, last visit | Matches your units and the reason he came | MDG Annexure 6 |
| Yes/no checks: delivery rate, filters, hoses and nozzles for leaks, tank openings, wiring | Every line answered | MDG Annexure 6 |
| Weights & Measures seal calibration | A broken seal, if found, is written in the report and you sign too | MDG 4.3(a) |
| Water dip in cm | A figure is entered. MDG has the representative dip for water on every visit | MDG 4.4 |
| Tank interconnection and unauthorised fittings | Both answered. MDG classes an unauthorised fitting in a dispenser and an unauthorised connection between tanks as critical irregularities | MDG Annexure 6 MDG 5.1.4 MDG 5.1.5 MDG 8.2 |
| Silica gel on the vent of ethanol-blended MS | Answered | MDG Annexure 6 |
| Repairs, parts replaced, parts required | Listed. After a major pipeline leak, the totaliser reading and tank dip are noted too, and you sign | MDG 4.3(b) |
| Date, arrival and departure times, signatures | Times are right; both signatures | MDG Annexure 6 |
The form has three copies and the outlet gets the second MDG Annexure 6. For who fixes what, see breakdowns and leaks.
Before you sign
General practice, not an MDG rule: do not sign with a blank line; ask for the missing entry to be written in front of you. For example, if the fitter replaced a hose but left "parts replaced" and the departure time empty, have both filled first.
Clause 4.3(a) calls the report the pump maintenance report MDG 4.3(a), and MDG asks for pump maintenance records of the current and previous financial years MDG 5.1.12(ii). General practice, not an MDG rule: keep your copy with them.
What MDG does not say
MDG does not say what happens if the dealer does not sign, or whether he may add a remark of his own. Ask your oil company.
Questions dealers ask
01What do I check on the fitter's job report before I sign?
The form records the visit and equipment details, the yes/no checks, the water dip in cm, the repairs and parts, and the times MDG Annexure 6. In practice, read each before you sign. MDG has a broken seal and a major pipeline leak written into the report MDG 4.3(a) MDG 4.3(b), so look for them there.
02Why does the report carry a water dip?
MDG has the company's representative dip the underground tanks for water on every visit to each outlet, and the report has a line for the reading in cm MDG 4.4 MDG Annexure 6.
03What if the fitter finds a broken Weights & Measures seal?
He informs the concerned company official and enters it in the pump maintenance report, which you sign too MDG 4.3(a).
04How long should I keep the job report?
MDG asks for pump maintenance records of the current and previous financial years MDG 5.1.12(ii), and clause 4.3(a) calls the fitter's report a pump maintenance report MDG 4.3(a). General practice, not an MDG rule: keep your copy for that time.
Read the official text: Marketing Discipline Guidelines 2024 (PDF on Bharat Petroleum's website) (also published on iocl.com).