Facts checked on 26 November 2026. Published by MDG Services on 26 November 2026.
1. The land, ready for building
Within 2 months (Group 1) or 4 months (Group 2) of the letter of intent, you make the land available with all its documents Selection brochure June 2023, cl.16. Before the oil company invests anything, the land must be developed to road level, with the entry, exit and service lanes, a retaining wall and a compound wall at least 1.5 metres high, as the company approves Selection brochure June 2023, cl.4 Note 1. On a dealer-owned site the land must be in your name or leased to you for the advertised period; on a company-owned site it must be registered in the company's name by long lease or sale Selection brochure June 2023, cl.4(vi).
2. Approvals and the PESO licence
The company prepares the layouts and the applications for statutory approvals and licences. You coordinate with the authorities for every NOC, and you must obtain the approvals needed to run the outlet Selection brochure June 2023, cl.8(D). Under the Petroleum Rules, PESO first sanctions the plans and specifications of the premises Petroleum Rules 2002, rule 131, and the District Authority decides on a no-objection certificate for the site plan, within three months of receiving the application Petroleum Rules 2002, rule 144. Details are on the PESO licence and applying online.
3. Building: who provides what
| Item | Company-owned site | Dealer-owned site |
|---|---|---|
| Developed land, lanes and walls | Dealer | Dealer |
| Tanks, dispensers, signs, automation | Oil company | Oil company |
| Sales office, toilet, electricity and water connections | Oil company | Dealer |
| Driveway and canopy | Oil company | Dealer |
| Generator or inverter | Dealer | Dealer |
All rows from the brochure Selection brochure June 2023, cl.8. The dealer also provides the fire-fighting and safety equipment Selection brochure June 2023, cl.8(B). The fixed fee (dealer-owned) or total bid (company-owned) is due within 15 days of receiving the NOC, and the company starts installing only after it is paid Selection brochure June 2023, cl.13. The approximate investment is stated in the advertisement Selection brochure June 2023, cl.8(C).
4. Appointment and commissioning
- Pay the interest-free security deposit, for example Rs 5 lakh for a regular outlet in the Open category, less the 10% already paid Selection brochure June 2023, cl.20.
- Give a fresh affidavit Selection brochure June 2023, cl.19.
- Receive the letter of appointment with the executed dealership agreement, before commissioning Selection brochure June 2023, cl.19.
If progress falls behind the LOI's timelines without a justifiable reason, the LOI is withdrawn Selection brochure June 2023, cl.19. For the weights-and-measures side of the dispensers, see metrology.
Where this comes from
- Selection brochure, June 2023: cl.4, cl.8, cl.13, cl.16, cl.19, cl.20.
- Petroleum Rules 2002, PESO: rules 131 and 144.
Questions people ask
01What is the petrol pump construction process?
Land developed by you, layouts and approvals prepared by the oil company, the fixed fee or bid paid, then the company's tanks, dispensers and other facilities installed Selection brochure June 2023, cl.8, cl.13, cl.16. The split of work depends on the site type, shown in the table on this page.
02How much does it cost to build a petrol pump?
The guideline gives no single figure. The approximate investment for infrastructure, facilities and working capital is stated in each advertisement Selection brochure June 2023, cl.8(C). See what it costs for the fixed fees and deposits.
03What is the letter of appointment for a petrol pump?
The letter that appoints you as dealer. It is issued before commissioning, along with the executed dealership agreement, after the security deposit and a fresh affidavit Selection brochure June 2023, cl.19, cl.20.
04How long from LOI to opening?
No total is fixed. The LOI sets its own timelines, and the LOI can be withdrawn if progress falls behind them without a justifiable reason Selection brochure June 2023, cl.19. The stage limits before the LOI are on the selection process page.